I have a Date Type metric dimensioned by Project and Month. The “Project” Dimension has an Integer Property of “Relative Completion Day”. Number of Days can be positive or negative.
I am attempting to calculate a date based on adding “Relative Completion Day” property to the First Workday of the Next Month (M-F). Below is an Example of how it would Ideally Work.
What would be the best formula for this? I have also screenshotted my Day dimension.
Project Dimension:

Calculated Date: (2/3/2025 + (-3) = 1/29/2025) ; 2/3/2025 is the first workday of February - 3 workdays before that.

Day Dimension: